Moulded side/sole outlet

  • nsure the gutter around the side sole outlet hole is clean and dry. Blow dry with heat gun if damp
  • Continue to roll liner two metres beyond the outlet hole ensuring the liner is pressed firmly into the gutter creases. This will prevent air pockets and form a solid base to weld the outlet to the liner
  • Using a Stanley knife, cut around the outlet hole until the full outlet capacity has been achieved
  • Pin the liner around the outlet hole. Two pins on the gutter sole 35mm from the crease line and two pins on the gutter slope 35mm from the crease line. Outlet size will determine the quantity of fixings required
  • Ensure Sharmans Fixing Caps are installed over all fixings prior to welding
  • Push the side sole outlet through the hole in the liner ready for welding
  • The weakest point of any weld is the crease lines on the gutter sole
  • Weld the side sole outlet at these points first ensuring the moulded unit is pressed firmly into the gutter creases
  • Fully weld the flange on the outlet to the gutter sole followed by the gutter slope to complete the installation
  • Allow the outlet to cool before probe testing the weld
  • Any un-welded area’s will have to be re-welded and again probe tested once cool

Image placeholder