Moulded side chute
- Ensure the gutter around the side chute is clean and dry. Blow dry with heat gun if damp
- Continue to roll the liner two metres beyond the side chute
- Using a Stanley knife, cut the liner around the side chute until the section of liner can be removed
- Pin the liner around the side chute using the specified fixings
- Ensure Sharmans Fixing Caps are installed over all fixings prior to welding
- Push the side chute through the hole until it sits flush with the gutter slope ready for welding
- Fully weld the flange to the liner all around the side chute
- Allow the side chute to cool before probe testing the weld
- Any un-welded area’s will need to be re-welded and again probe tested once cool