Moulded side chute

  • Ensure the gutter around the side chute is clean and dry. Blow dry with heat gun if damp
  • Continue to roll the liner two metres beyond the side chute
  • Using a Stanley knife, cut the liner around the side chute until the section of liner can be removed
  • Pin the liner around the side chute using the specified fixings
  • Ensure Sharmans Fixing Caps are installed over all fixings prior to welding
  • Push the side chute through the hole until it sits flush with the gutter slope ready for welding
  • Fully weld the flange to the liner all around the side chute
  • Allow the side chute to cool before probe testing the weld
  • Any un-welded area’s will need to be re-welded and again probe tested once cool