Option 1 – Where the insulation is flush with the gutter edge

** Ensure the roof sheet overhangs the insulation by 70mm further than the finished edge of the gutter liner to prevent capillary action **

** This method can also be used if the insulation overhangs the gutter by 40mm or less **

  • Fit the liner to the full profile of the gutter
  • Turn back the liner onto the underside of the roof sheet
  • Using Sharmans fixings, mechanically fix a 30mm x 30mm galvanised angle flashing at 500mm centres

 